30A Detour Grayton to Blue Mountain Big Redfish Lake Bridge Construction

Discussion in 'All About SoWal' started by kurt, Jul 5, 2016.

  1. kurt

    kurt Admin Staff Member

    Joined:
    Oct 15, 2004
    Messages:
    7,029
    Likes Received:
    3,664
    Location:
    SoWal
    Big Redfish Drainage Improvement Project- This project will replace the existing culverts on Co Hwy 30A at Big Redfish Lake with a new bridge. The new bridge will upgrade the drainage capacity on Co Hwy 30A at Big Redfish Lake which has seen substantial damage during past storm events.

    By removing the existing culverts, this project will also provide an environmental benefit by allowing the lake to function in a more natural state. All engineering, design, and permitting is complete and utility relocations are scheduled to take place in early 2017. Construction of this project is currently scheduled for after Labor Day 2017. This project is being provided by a HMGP grant from FEMA with additional funding provided by the Walton County Board of County Commissioners.

    Walton County
     
  2. SoWal Staff

    SoWal Staff Serving the Community! Staff Member

    Joined:
    Apr 14, 2006
    Messages:
    2,791
    Likes Received:
    203
    Location:
    South Walon, FL
    Project on schedule - the $603, 450 cost is paid by Florida Division of Emergency Management Hazard Mitigation grant
     
  3. steel1man

    steel1man Beach Fanatic

    Joined:
    Jan 10, 2013
    Messages:
    2,042
    Likes Received:
    404
    bids opened:
    Bid Number: 017-027
    Bid Title: BRIDGE MATERIAL FOR BIG REDFISH BRIDGE IMPROVEMENTS
    Category: Public Works Road Construction
    Status: Awarded
    Additional Status Information: BCC awarded 08/08/2017
    Bid Recipient: Conecuh Bridge & Engineering, Inc.
     
  4. kurt

    kurt Admin Staff Member

    Joined:
    Oct 15, 2004
    Messages:
    7,029
    Likes Received:
    3,664
    Location:
    SoWal
    HMGP BIG REDFISH LAKE BRIDGE IMPROVEMENTS

    The Board of County Commissioners, "The County" is seeking competitive bids from qualified contractors to construct the following project.
    This project consists of constructing a new 68 foot concrete two-span vehicular bridge on concrete pilings on County Road 30-A. The project also includes demolition of the existing double metal culvert on County Road 30-A along with earthwork activities and rip-rap to stabilize the slopes under the proposed bridge. The bridge approaches will constructed with a brick paver surface along with demolition and removal of the existing roadway each direction from the bridge approximately 150 linear feet with new limerock base and asphalt proposed.

    LATE SUBMITTALS RECEIVED AFTER THE FOREMENTIONED DEADLINE DATE, EITHER BY MAIL, OR OTHERWISE, WILL NOT BE CONSIDERED AND RETURNED UNOPENED. THE TIME OF RECEIPT WILL BE DETERMINED BY THE TIME RECEIVED IN THE PURCHASING AGENT’S OFFICE. IT IS THE SOLE RESPONSIBILITY OF THE FIRM FOR ASSURING THAT THE SUBMITTAL IF RECEIVED IN THE PURCHASING OFFICE BY THE DESIGNATED DATE AND TIME. NO FAXED, ELECTRONIC OR ORAL SUBMITTAL WILL BE ACCEPTED.

    BIDDER IS RESPONSIBLE FOR THE DELIVERY OF IT'S SUBMITTAL. SUBMITTALS RECEIVED AFTER THE SPECIFIED DAY AND TIME WILL NOT BE OPENED. THE PURCHASING DEPARTMENT IS CLOSED ON ALL FRIDAYS.

    To be considered, contractor shall submit one original and three (3) copies of the submittal in a sealed envelope or package, clearly marked with the contractors' name and address, and the words "BIG REDFISH LAKE BRIDGE IMPROVEMENTS.

    Bid closes on September 7, 2017 at 10:00AM (local time) and will be opened immediately thereafter.
     
  5. kurt

    kurt Admin Staff Member

    Joined:
    Oct 15, 2004
    Messages:
    7,029
    Likes Received:
    3,664
    Location:
    SoWal
    HMGP BIG REDFISH LAKE BRIDGE IMPROVEMENTS

    The Board of County Commissioners, "The County" is seeking competitive bids from qualified contractors to construct the following project.

    This project consists of constructing a new 68 foot concrete two-span vehicular bridge on concrete pilings on County Road 30-A. The project also includes demolition of the existing double metal culvert on County Road 30-A along with earthwork activities and rip-rap to stabilize the slopes under the proposed bridge. The bridge approaches will constructed with a brick paver surface along with demolition and removal of the existing roadway each direction from the bridge approximately 150 linear feet with new limerock base and asphalt proposed.

    LATE SUBMITTALS RECEIVED AFTER THE FOREMENTIONED DEADLINE DATE, EITHER BY MAIL, OR OTHERWISE, WILL NOT BE CONSIDERED AND RETURNED UNOPENED. THE TIME OF RECEIPT WILL BE DETERMINED BY THE TIME RECEIVED IN THE PURCHASING AGENT’S OFFICE. IT IS THE SOLE RESPONSIBILITY OF THE FIRM FOR ASSURING THAT THE SUBMITTAL IF RECEIVED IN THE PURCHASING OFFICE BY THE DESIGNATED DATE AND TIME. NO FAXED, ELECTRONIC OR ORAL SUBMITTAL WILL BE ACCEPTED.

    BIDDER IS RESPONSIBLE FOR THE DELIVERY OF IT'S SUBMITTAL. SUBMITTALS RECEIVED AFTER THE SPECIFIED DAY AND TIME WILL NOT BE OPENED. THE PURCHASING DEPARTMENT IS CLOSED ON ALL FRIDAYS.

    To be considered, contractor shall submit one original and three (3) copies of the submittal in a sealed envelope or package, clearly marked with the contractors' name and address, and the words "BIG REDFISH LAKE BRIDGE IMPROVEMENTS.

    Bid closes on September 7 28, 2017 at 10:00AM (local time) and will be opened immediately thereafter.
     
  6. steel1man

    steel1man Beach Fanatic

    Joined:
    Jan 10, 2013
    Messages:
    2,042
    Likes Received:
    404
    Will not know the cost until September 28,2017
     
  7. kurt

    kurt Admin Staff Member

    Joined:
    Oct 15, 2004
    Messages:
    7,029
    Likes Received:
    3,664
    Location:
    SoWal
    Big Redfish Lake Bridge Closing – The bids have been received and will be considered for award at the next BCC meeting on Oct 10th.

    There is an alternate price to be considered by the board to complete the project in 60 days as opposed to the 90 day base bid.

    Road will be closed starting October 23rd at the bridge site. Multi-use path will be closed starting Oct 16th for utility relocates.
     
  8. ejr1122

    ejr1122 Beach Comber

    Joined:
    Aug 1, 2016
    Messages:
    17
    Likes Received:
    2
    Location:
    Santa Rosa Beach
    Is there an ETA on when the road and/or path will reopen?
     
  9. steel1man

    steel1man Beach Fanatic

    Joined:
    Jan 10, 2013
    Messages:
    2,042
    Likes Received:
    404
    One bid was for 60 days
    More where for 90
    Who knows who won....first week limited work....6" gas line welded in line sitting on 30A.
     
  10. Jenksy

    Jenksy Beach Fanatic

    Joined:
    Oct 25, 2012
    Messages:
    658
    Likes Received:
    108
    Something needs to be done about the detour intersections on 98 - traffic is backed up on grayton rd going north. Need to change the light frequency or get a traffic cop.
     
  11. John G

    John G Beach Fanatic

    Joined:
    Jul 16, 2014
    Messages:
    1,804
    Likes Received:
    297
    Agree. I would move for Citizen Service Officer Leah to spearhead the whole thing. She is more than capable and should be paid as a full time staff member. She's out directing traffic at almost every wreck.
     
  12. raven316

    raven316 Beach Lover

    Joined:
    Nov 12, 2007
    Messages:
    100
    Likes Received:
    8
    Location:
    Athens, GA
    Is it done yet?
     
  13. TJMay

    TJMay Beach Lover

    Joined:
    Jul 25, 2005
    Messages:
    165
    Likes Received:
    51
    Now that's funny...
     
  14. steel1man

    steel1man Beach Fanatic

    Joined:
    Jan 10, 2013
    Messages:
    2,042
    Likes Received:
    404
    Oh yeah, finished last week, also paved 30A from 83 to Grayton and finished replacing ALL bike paths....this message will be released around Mid-February.
    If your lucky.....
     
  15. Low Brow

    Low Brow Beach Lover

    Joined:
    Jan 13, 2014
    Messages:
    55
    Likes Received:
    7
    When is it supposed to be open again?
     
  16. Jimmy T

    Jimmy T Beach Fanatic

    Joined:
    Apr 6, 2015
    Messages:
    473
    Likes Received:
    147
    End of January, but I wouldn' be surprised if it takes longer.
     
  17. steel1man

    steel1man Beach Fanatic

    Joined:
    Jan 10, 2013
    Messages:
    2,042
    Likes Received:
    404
    Was by there today...No way it's ready in 3 weeks...plus 30A is scheduled for repaving and doubt bridge will open until that area is repaved and also bike paths are being torn up,and replaced....lots going on in this area..
     
  18. TJMay

    TJMay Beach Lover

    Joined:
    Jul 25, 2005
    Messages:
    165
    Likes Received:
    51
    Latest I heard is for completion the end of March!
     
  19. Jimmy T

    Jimmy T Beach Fanatic

    Joined:
    Apr 6, 2015
    Messages:
    473
    Likes Received:
    147
    Yikes!
     
  20. kurt

    kurt Admin Staff Member

    Joined:
    Oct 15, 2004
    Messages:
    7,029
    Likes Received:
    3,664
    Location:
    SoWal
    These photos are from 10 days ago on 1/3/18. I guess 430 pm is too late in the day to be working.