Construction Update
October 23, 2008
Construction on the airport remains ahead of schedule.
Walbridge, the company slated to build the terminal building and all support buildings, received the notice to proceed (NTP) on October 15 and has set up their construction office on site. Work will begin within 30 days.
Runway 16-34:
Construction Update
October 23, 2008
Construction on the airport remains ahead of schedule.
Walbridge, the company slated to build the terminal building and all support buildings, received the notice to proceed (NTP) on October 15 and has set up their construction office on site. Work will begin within 30 days.
Runway 16-34:
- The asphalt base is ongoing and is approximately 20% complete.
- Concrete paving on Runway 16-34 is expected to begin November 11.
- Runway lighting is ongoing and is nearing 19% completion.
- Earthwork is nearing 97% completion.
- Asphalt paving and the lighting work are ongoing.
- Stabilized Sub Grade is complete.
- Curbing is approximately 98% complete.
- The limerock base is layer is going down and is nearly 75% complete.
- Complete
- Work is proceeding east and west of the runway and is 58% complete.
- Earthwork is nearing completion