Hard to believe that the original thread started in 2008, and nearly 10 years later, nothing has happened.

Right hand turn lanes will just make the intersection more dangerous to pedestrians.
 

Kurt

Admin
Staff member
Oct 15, 2004
2,234
4,926
SoWal
mooncreek.com
ITB 017-029 CR30A RESURFACING PROJECT PHASE 3 (CR83 TO CR395)

CR30A RESURFACING PROJECT PHASE 3 (CR83 TO CR395)


The Board of County Commissioners, Walton County, Florida (the “County”) is seeking competitive bids for the CR30A Resurfacing Project Phase 3 (CR83 to CR395).

ITB DEADLINE: November 6, 2017 no later than 3:00PM (local time) and will open immediately thereafter.

PROJECT: The Walton County Road 30A Resurfacing Project (CR 83 to CR 395) is located in Santa Rosa Beach south of US Hwy 98. The scope of the proposed project will involve roadway rehabilitation along CR 30A from the intersection of CR 83 in Blue Mountain Beach to the intersection of CR 395 in Seagrove. The contractor will be required to mill and remove the existing asphalt pavement to and average depth of two inches throughout the mainline and paved shoulders within the project limits and deliver the reclaimed asphalt to the County’s pit on CR 83 in Blue Mountain Beach. Following milling operations, the contractor will be required to replace the milled surface with FC 12.5, 220 lb/sy (2” compacted thickness). The contractor will be required to provide Maintenance of Traffic throughout the duration of the construction timeframe and will be responsible for coordinating, inventorying, and replacing all pavement striping and markings removed and/or damaged during the construction process. Clipping of shoulders will be required prior to completion of the roadway rehabilitation efforts.

LATE BIDS RECEIVED AFTER THE AFOREMENTIONED DEADLINE DATE, EITHER BY MAIL OR OTHERWISE, WILL NOT BE CONSIDERED AND RETURNED UNOPENED. THE TIME OF THE RECEIPT WILL BE DETERMINED BY THE TIME RECEIVED IN THE PURCHASING AGENT’S OFFICE. BIDS OFFERED ARE THE SOLE RESPONSIBILITY OF THE VENDOR FOR ASSURING THAT BIDS ARE RECEIVED IN THE PURCHASING OFFICE BY THE DESIGNATED DATE AND TIME. NO FAXED, ELECTRONIC, OR ORAL BIDS WILL BE ACCEPTED.


BIDDER IS RESPONSIBLE FOR THE DELIVERY OF ITS BID. BIDS RECEIVED AFTER THE SPECIFIED DAY AND TIME WILL NOT BE OPENED.

THE PURCHASING DEPARTMENT IS CLOSED ON ALL FRIDAYS.


All questions in regards to this bid are to be directed in writing to the County Purchasing Agent. Questions must be submitted no later then 12:00 Noon on October 25, 2017. DIRECTING QUESTIONS TO ANY OTHER COUNTY STAFF, ROJECT ENGINEER OR ANY OTHER PERSON IS PROHIBITIED AND WILL RESULT IN YOUR BID BEING FOUND NON-RESPONSIVE.

Mandatory Pre-Bid will be held on October 19. 2017 at 9:00AM at the Public Works Conference room, located at 117 Montgomery Circle, DeFuniak Springs, FL 32435.


To be considered, Bidders must submit an original and three (3) copies of the ITB in a sealed envelope or package, clearly marked with the Bidder’s name, address, and the words “CR30A RESURFACING PH 3 - CR83 to CR395” addressed to:

Office of Central Purchasing 176 Montgomery Circle
DeFuniak Springs, Florida 32435
 

steel1man

Beach Fanatic
Jan 10, 2013
2,291
659
30A staring at Hwy 83 going east Busy Fall/Winter:

Sealed bids for the Multi-Use Path Renovations CR83 - CR283 will be received by the Board of County Commissioners, Walton County, Florida, hereinafter referred to as "the County" at:
Office of Central Purchasing
176 Montgomery Circle
DeFuniak Springs, FL 32435

MANDATORY PRE-BID will be held on October 23, 2017 at 9:00AM local time and will be held at the Walton County Tourist Development Council Visitor Center Conference Room located at 25777 US Hwy 331 S., Santa Rosa Beach, FL 32459.

Closing date is November 16, 2017 at 3:00PM Local Time and will open immediately thereafter.

All questions in regards to this bid are to be directed in writing to the County Purchasing Agent. Questions must be submitted no later then 12:00 Noon on October 30, 2017.
DIRECTING QUESTIONS TO ANY OTHER COUNTY STAFF, ROJECT ENGINEER OR ANY OTHER PERSON IS PROHIBITIED AND WILL RESULT IN YOUR BID BEING FOUND NON-RESPONSIVE.

PROJECT OVERVIEW:

This project includes the renovation of the Timpoochee Trail along the south side of CR 30A beginning at CR 83 (Old Blue Mountain Rd) in the west and ending at CR 283 (Defuniak St) in the east. The project intent is to construct a 10’ trail along the south side of CR 30A and provide storm drainage facilities and other enhancements not currently in place. Pavement removal, earthwork, grading, base material construction, asphalt paving, concrete work, paver replacement, storm drainage, retaining walls, sodding, and signing & marking activities are all required in the scope of work. Repair and/or replacement of the wooden bridges at Big Redfish Lake, Little Redfish Lake, and Alligator Lake are also required. Careful coordination with existing utilities and the roadway bridge replacement project at Big Redfish Lake are required. See contract plans for exact details and requirements.