Should have picked the 60 day guy..(finished around 12/23) .. 90 days appox.1/23/18.....well that isn't happening!! Best guess based on progress as of 1/12/18 earliest maybe 2/23/18 +/-Big Redfish Lake Bridge Closing – The bids have been received and will be considered for award at the next BCC meeting on Oct 10th.
There is an alternate price to be considered by the board to complete the project in 60 days as opposed to the 90 day base bid.
Road will be closed starting October 23rd at the bridge site. Multi-use path will be closed starting Oct 16th for utility relocates.