Construction Update: 10/01/2009
by NewPFN on October 5, 2009
Contract 1: Heavy Civil and Airfield Lighting
The project is currently 92% complete with 78% of the contract utilized.
The project is 56% complete with 59% of the time utilized.
Terminal Building
Utilities are 65% complete with 71% of the contract time utilized.
The landscape contract is 45% complete with 23% of the contract time utlilized.
by NewPFN on October 5, 2009
Contract 1: Heavy Civil and Airfield Lighting
The project is currently 92% complete with 78% of the contract utilized.
- Grading of the longitudinal ditches continues.
- In the General Aviation Area the taxiways are being regarded and limerocked. All 6 taxiways in the GA area will have final asphalt in two weeks.
- All of the General Aviation area and Terminal support area are expected to have asphalt by the end of October.
- Installation of light cans and conduits is underway on the South end of the airfield.
- Sod is currently being installed along the Runway Clear Zone.
- Of the project site’s 1,400 acre foot print, more than 1,000 acres has been either seeded or paved.
The project is 56% complete with 59% of the time utilized.
Terminal Building
- Completing the roof deck on the east side of Area B.
- Continuing installation of windows on the east side of Area A.
- Completing storefront installation down the west elevation of the building.
- Continuing installation of CFMF at interior walls in the Baggage Handling System.
- Continuing with MEP at Baggage Handling area.
- The tower cab is now in place bringing the height of the ATCT to 147 feet.
- Continuing installation of the exterior stairs up to tower cab.
- Beginning MEP installation.
- Completing MEP installations.
- Beginning to set steel at administration roof.
- Installation of exterior CMU walls continues
- Excavating for spread footings at fuel island canopy
- Site grading continues
Utilities are 65% complete with 71% of the contract time utilized.
- Power systems are scheduled to be energized by September 15 and water will be provided to the terminal complex in October.
- Street light installation - 97% complete. Light poles being installed.
- 12″ water main - 99% complete.
- 8″ sanitary force main - 100% complete. 16,387 lf completed onsite and along CR-388.
- 3W2″ power distribution - 98% complete. Primary power energized.
- Street Light duct work - 34,165 lf installed on west side of main road.
- 6Wx4″ - 100% complete. 6,849 lf concrete encased communication duct bank.
- 30″ water main - 98% complete. Testing underway.
- 24″ water main - 98% complete. 7,878′ lf installed along Joyner Road.
- Lift Station - 55% complete. Plumbing installation continuing.
- Booster Pump station - 50% complete. Tanks complete, plumbing underway.
- Fuel Farm Facility - 45% complete. Slab poured, 110cy of concrete
- Triturator - 20% complete. Vault installation continuing.
- 68 fire hydrants installed
The landscape contract is 45% complete with 23% of the contract time utlilized.
- Regrading swales on Main Access Road.
- Installing sod along the Main Access Road.
- Installing erosion control mat on site.
- Hydroseeding.
- * Contract awarded to Hypower, Inc.
- * Base bid amount $1,728,800.00.
- * Bid Alternate 1 for installation of RWY Centerline and Touchdown Zone Lighting $311,400.00.
- * Anticipated Notice to Proceed is September 1, 2009.
- * Construction duration is 180 days.
- RWY 16 Instrument Landing System - 90 days
- RWY 16 Medium Intensity Approach Light System - 120 days
- RTR Shelter & Tower Installation - 150 days
- Air Traffic Control Tower Equipment Installation - 150 days
- Automated Surface Observation System site preparation - 180 days
Which ones have direct flights now into PCB?