Draper Lake Bridge Construction Project Update #1
The Draper Lake Bridge Construction Project has been under way for the last two weeks. Currently, the utility contractors are scheduled to be complete with the associated utility relocations by the end of this week.
A pre-construction meeting will be held on Tuesday, October 6th at which time the notice to proceed will be issued to Murphree Bridge Corporation. The construction contract is a 120 day contract and the project currently remains on schedule which will allow County Highway 30A to reopen no later than March 1, 2016.
If you have any questions related to this project please do not hesitate to contact Walton County Public Works at 892-8108.